Our Milestone team has been working full steam ahead on Phase III of the Fullerton Pike Corridor Reconstruction Project. The project aims to provide east to west connectivity on the south side of Bloomington and ease traffic congestion on and off I-69 into the heart of Bloomington.
Previous phases on the reconstruction project began in 2019 and include a roundabout at the intersection of Gordon Pike and Clearview Drive, a traffic signal installation at Fullerton Pike and Rockport Road, intersection at Wickens Street and Falcon Drive, as well as several other upcoming improvements. You can find the full detailed list from the Monroe Highway Department here.
Currently on Phase III of the project, our Milestone team is working on the completion of a 525-foot bridge. The bridge is the largest part of the almost $19 million dollar project, and once complete, it will be the largest bridge in Monroe County.
During the last week of August, Mike McCory and Jeff Livington’s crews set over 90-ton beams to prepare for the bridge’s concrete pour.
Coordinating how to get 90-ton beams to a jobsite was a challenge, but Mike McCory says, “What doesn’t challenge you doesn’t grow you.”
Setting this large of beams took extra dedication to safety and communication to make sure they were placed effectively. Mike was proud of his team, and this was many team members’ largest beam setting yet.
As they look to the finish line, the team is looking forward to the bridge pour that begins this October and seeing the positive impact the project will bring to the Bloomington community.
If you would like to learn more about the Fullerton Pike Reconstruction Project, you can find recent story coverages linked from The Herald-Times and WTIU/WFIU.
Boost This Post
29
At Milestone, we are committed to Making Lives Better One Road and Bridge at a Time. Central to this mission is the continuous improvement of our facilities and processes across the state. A prime example is the recent investment in upgrades at the Terre Haute plant this past fall and winter. These enhancements are expected […]
Read MoreBoost This Post
7
This winter, our asphalt and concrete divisions were celebrated for their award-winning projects and achievements in 2024. ACPA Awards In December, Milestone team members traveled to Arizona to attended American Concrete Pavement Association’s (ACPA) National Excellence in Concrete Paving Awards Gala. For over 30 years, the awards program has recognized contractors, engineers and project owners […]
Read MoreBoost This Post
3
In 2021, our Milestone team began work on Section 6 Contract 5, the final component of the I-69 Finish Line Project, which establishes a direct connection between Evansville and Indianapolis. This largest contract of the project includes improvements and added travel lanes to I-465 on the southwest side of Indianapolis, stretching from I-70 to I-65. […]
Read MoreBoost This Post